From Vision to Verdict: A Longitudinal Analysis of Cost Escalation and Risk Management in the Stuttgart 21 Megaproject

Prof. Dr.-Ing. Klaus Richter , Institute for Infrastructure and Project Management, Technical University of Munich, Munich, Germany
Jonas Baumann , Centre for Civil Engineering and Geosciences, ETH Zürich, Zurich, Switzerland

Abstract

Purpose: This paper provides a longitudinal analysis of the Stuttgart 21 (S21) megaproject, dissecting the evolution of its fiscal planning and risk management to identify the root causes of its severe cost overruns and protracted stakeholder disputes.

Design/methodology/approach: The study employs a qualitative, single-case study methodology. It synthesizes over three decades of data from official project documents, including the original feasibility study and financing contract; government and legal records, notably the 2024 court ruling on cost liability; academic literature; and chronological media archives. The analysis traces the project's financial trajectory against key risk events and governance decisions.

Findings: The project's initial €4.5 billion budget, established in a 2009 financing agreement, was founded on optimistic assumptions that failed to account for significant technical, geological, and political risks. The rigid contractual framework proved incapable of managing emergent challenges, leading to a cost escalation to over 11 billion. This triggered a legal battle where project owner Deutsche Bahn sought to compel partners to cover the deficit. This culminated in a landmark 2024 court decision that rejected Deutsche Bahn's claim, assigning the financial burden of the overruns almost entirely to the company. The core failures identified were an inadequate initial risk assessment, an inflexible governance structure, and a profound underestimation of project complexity.

Practical implications: The S21 case serves as a critical lesson for megaproject practitioners and policymakers. It underscores the necessity of independent and pessimistic forecasting, the establishment of adaptive financing agreements with clear risk-sharing clauses, and robust governance to manage uncertainty over a project’s long lifecycle.

Originality/value: This paper offers a unique start-to-finish analysis of a major European megaproject, linking its initial financial architecture directly to the ultimate legal and financial fallout. It provides a comprehensive, evidence-based cautionary tale for the management of future megaprojects globally.

Keywords

Megaprojects, Stuttgart 21, Cost Overrun

References

Ashkanani, S., & Franzoi, R. (2022). An overview on megaproject management systems. Management Matters, 19(2), 129-148. https://doi.org/10.1108/MANM-01-2022-0006

Berman, K., & Knight, J. (2013). Financial intelligence. Harvard Business Review Press.

Böll, S. (2011, April 11). Grün-rot und stuttgart 21: Viel Geld, wenig Bahnhof. Der Spiegel. https://www.spiegel.de/wirtschaft/unternehmen/gruen-rot-und-stuttgart-21-viel-geld-wenig-bahnhof-a-759527.html

DB Projekt Stuttgart–Ulm. (n.d.). Stuttgart 21-Überblick. Retrieved August 6, 2025, from https://www.bahnprojekt-stuttgart-ulm.de/projekt/ueberblick/stuttgart-21/

Deutsche Bahn AG. (2022). Deutsche Bahn 2022 integrated report.

Deutsche Bahn. (n.d.). Architektur. Retrieved August 6, 2025, from https://www.bahnprojekt-stuttgart-ulm.de/projekt/stuttgart-filder-s21/neue-bahnhoefe/hauptbahnhof-stuttgart/architektur/

Deutsche Bahn AG. (1996). Die Machbarkeitsstudie | Projekt "Stuttgart 21".

Eduardo Yamasaki Sato, C., & De Freitas Chagas Jr, M. (2014). When do megaprojects start and finish? Redefining project lead time for megaproject success. International Journal of Managing Projects in Business, 7(4), 624-637. https://doi.org/10.1108/IJMPB-07-2012-0040

DB Netz AG, Land Baden-Württemberg, Landeshauptstadt Stuttgart, Verband Region Stuttgart, & Flughafen Stuttgart GmbH. (2009). Finanzierungsvertrag.

Flyvbjerg, B. (2017). Megaprojects: Over budget, over time, over and over. Cato Institute Policy Report. https://www.cato.org/policy-report/january/february-2017/megaprojects-over-budget-over-time-over-over

Baden-Württemberg.de. (2024, May 7). Gerichtsentscheidung über S-21-Mehrkostenklage der Bahn. Retrieved August 6, 2025, from https://www.baden-wuerttemberg.de/de/service/presse/pressemitteilung/pid/verwaltungsgerichtsentscheidung-zur-stuttgart-21-klage

DB Projekt Bau GmbH. (2011). Großprojekt Stuttgart 21-Wendlingen-Ulm Chancen und Risiken.

He, Q., Xu, J., Wang, T., & Chan, A. P. C. (2021). Identifying the driving factors of successful megaproject construction management: Findings from three Chinese cases. Frontiers of Engineering Management, 8(1), 5-16. https://doi.org/10.1007/s42524-019-0058-8

Hillson, D. (2003). Using a risk breakdown structure in project management. Journal of Facilities Management, 2(1), 85-97. https://doi.org/10.1108/14725960410808131

Hörger, D. (2023, May 8). Verwaltungsgericht verhandelt über Klage der Bahn zu "Stuttgart 21"-kosten. tagesschau.de. https://www.tagesschau.de/wirtschaft/finanzen/kosten-stuttgart-21-verhandlung-100.html

Houben, L. (2024, May 7). Stuttgart 21: Bahn muss Mehrkosten zahlen. ZDFheute. https://www.zdf.de/nachrichten/politik/deutschland/stuttgart-21-mehrkosten-urteil-deutsche-bahn-100.html

Hu, Y., Chan, A. P. C., & Le, Y. (2015). Understanding the determinants of program organization for construction megaproject success: Case study of the Shanghai Expo construction. Journal of Management in Engineering, 31(5), 05014019. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000310

Kaiser, S., & Windmann, A. (2010, October 1). The "Stuttgart 21" revolt: Protests against mega project grow. Der Spiegel. https://www.spiegel.de/international/germany/the-stuttgart-21-revolt-protests-against-megaproject-grow-a-713375.html

Article Statistics

Downloads

Download data is not yet available.

Copyright License

Download Citations

How to Cite

Prof. Dr.-Ing. Klaus Richter, & Jonas Baumann. (2025). From Vision to Verdict: A Longitudinal Analysis of Cost Escalation and Risk Management in the Stuttgart 21 Megaproject. International Journal of Economics Finance & Management Science, 10(09), 1–13. Retrieved from https://scientiamreearch.org/index.php/ijefms/article/view/171